Year of Completion: Invercargill - September 2013 / Mosgiel - August 2015

 

Construction Cost: Approx $1m

 

Brief description:

Project Management of the construction of new Childcare Centres in Invercargill and Mosgiel

 

Consultancy Requested:

  • Cost estimates and feasibilty advice

  • Preparation of contract documents

  • Tendering and appointment of main contractor

  • Project Management

  • Progress claim and variation assessment and certification

  • Bank drawdowns

  • Final account reconciliation